Offloading of windmill parts
9 sets of Goldwind windmills in transit to North Macedonia via Thessaloniki port.
A of total 200 units, 62006 CBM , 6485 tons.
Our Project Cargo team took care of unlashing / unwelding, offloading from FOB, customs entry formalities.
Overall supervision and co-ordination of all parties involved was a must, as well as overviewing the critical tandem lift arrangements as per vessel’s stowage plan.
The biggest vessel ever arrived at Thessaloniki port to discharge widmills!
And our team on the ground ready as always!
When #offloading #windmills #thinkofcosmatos
Scope
- Unlashing / unwelding at Thessalonik Port
- Offloading in tandem and single lift
- Port arrangements for temporary storage at port designated area
- Inward customs clearance formalities
Cargo
- 9 complete set of windmill parts with total volume 62000 cbm and weight 6500t
- 219 units in one shipment
- Heaviest unit generator 105t