Port Operation at Alexandroupolis
We have recently arranged the port operations at Alexandroupolis port for the FRSU project.
The whole project was completed in 5:30 hours.
No operational incidents or damages were reported.
Another project proving the specialty and experience of Cosmatos Group!
When in search of a #shipagent #alexandroupolis #port #thinkofcosmatos
Scope
- Liaise with port & customs authorities for the allocation of proper and adequate storage area close to the pier in order cargo to be reloaded on board an offshore vessel at a second operational stage.
- Booking of adequate stevedores on a short notice in order to offload the units ashore.
- Customs Clearance was received at 16:30 hrs and all parties were timely on standby so that discharging commenced at 16:45 hrs and completed at 22:15 hrs, losing no time at all.
- Overall Supervision and co-ordination of all parties involved, overviewing the critical tandem lift arrangements as per vessel’s stowage plan.
- In addition, on a ship husbandry attendance, we arranged for the requested ship provisioning & technician embarkation formalities.
Cargo
2 main units with dims & weights:
- 1 x PLEM Unit with dims 16.50 x 10.19 x 5.87 mtrs / 130.000 Kg.
- 1 x MUDMAT Unit with dims 16.21 x 12.22 x 2.50 mtrs / 45.000 Kg.
- 12 smaller parts/accessories.